P48, Spain's operating program

Curtailment & Congestion Updated: 2026-11-20

P48 is the label used for Spain's Programa Operativo, the operating program that incorporates the relevant scheduling information and real-time program modifications. It belongs to the system operator's program sequence rather than identifying a market product or restriction cause. REE explains its role in the technical-restriction process.

An evolving operating reference

An operating program is a versioned reference. New information, intraday outcomes or system instructions can change the program for a delivery period. The file publication time and the period to which a value applies are therefore different pieces of information.

The July 30, 2026 operating-procedure changes address, among other matters, P48 publication within the updated intraday information process. Data pipelines should use the relevant specification rather than assuming an old publication cadence remains unchanged.

Reading P48 alongside other data

The PDBF, PDVP and P48 describe different program references. Their values should be compared for the same unit and interval, keeping revisions separate from new quantities. Summing successive versions of the same interval would count a revised program more than once.

A P48 quantity is also different from a metered energy value. Comparing the two can be useful for examining a deviation, but requires consistent time resolution, unit mapping and measurement definitions. The program label alone does not identify a cause such as SCA or determine the applicable financial settlement.

For a project study, retain both delivery and publication timestamps and document the rule used to select the program version. Continue with the Explore on Spanish restriction codes for the distinction between a program, an operational cause and a change in energy.

Related Keywords

P48, Spain's operating programSpain