PDBF, Spain's base daily operating program

Curtailment & Congestion Updated: 2026-11-20

PDBF means Programa Diario Base de Funcionamiento, Spain's base daily operating program. It combines the relevant day-ahead market result and nominated physical bilateral positions into the reference program used before the daily technical-restriction process. REE describes this sequence in its adjustment-services guide.

A reference program, not a final outcome

The PDBF is a program snapshot for the delivery periods concerned. It is not a promise that every scheduled MWh will ultimately be physically produced or consumed. Security corrections, subsequent markets and later operating processes can modify the relevant positions.

ESIOS interfaces may use the shorter label PBF for the same base-program context. When combining sources, verify the file or indicator definition and delivery date rather than relying on a similar label alone. Keep the unit and interval resolution consistent.

Role in restriction analysis

Phase 1 of the daily restriction process identifies security corrections against the base program. Phase 2 subsequently restores generation-demand balance while respecting the security limitations. The resulting daily program is represented by the PDVP.

In an illustrative calculation, comparing a later 18 MWh program with a 20 MWh PDBF quantity gives a 2 MWh program difference for the same unit and interval. Attributing that difference to a specific restriction requires the corresponding process records. It is not automatically the plant's physically available renewable energy that was lost.

For a project assessment, retain the source version, UP or UF identifier, delivery interval and the stage to which each quantity belongs. The Explore on Spanish restriction codes explains how this program context supports the interpretation of restriction causes and energy adjustments.