Spain's transmission-grid planning toward 2030

Grid Access & Permitting Updated: 2026-11-20

Spain's transmission-grid planning toward 2030 sets out the development of the electricity transmission network over that horizon. It identifies planned reinforcements and new infrastructure to support demand, renewable integration and security of supply. MITECO announced the Council of Ministers' approval on November 20, 2026. The term Planificación 2025–2030 also appears in references to the planning cycle.

The approved planning framework and the physical network in service are different inputs to a project assessment. A planned line or substation does not provide usable capacity before its relevant works, authorizations and commissioning have taken place.

Planning status and connection decisions

For a particular node, identify the specific planned works and their relationship to the connection under study. Distinguish the approved plan, subsequent modifications, implementation progress and the network configuration available in each modeled year.

The presence of an investment in the plan does not grant an individual project's access or connection permission. Nor does a national investment total quantify the capacity available to that project. The grid-access Explore page explains the separate technical and administrative questions.

Using the plan in scenarios

A useful study can compare the existing network with defined future network configurations. Each scenario should state which reinforcements are assumed to be in service and when. A delayed commissioning case can help assess the consequence of depending on a particular investment.

These are scenario assumptions, not predictions of delivery or guarantees that all operating restrictions will disappear. Demand, generation, topology, outages and security criteria still affect results.

For location screening, The Map can provide context for selecting the next analysis. Project decisions require checking the relevant planning documents, their current implementation status and the applicable generation or demand access specifications.